13. As soon as the project proponent publishes the notice referred to in section 11, the project proponent sends a copy of the summary of the project’s impact assessment statement to any local municipality or Indian reserve in the territory of which the project will be carried out.
O.C. 287-2018, s. 13.
In force: 2018-03-23
13. As soon as the project proponent publishes the notice referred to in section 11, the project proponent sends a copy of the summary of the project’s impact assessment statement to any local municipality or Indian reserve in the territory of which the project will be carried out.
O.C. 287-2018, s. 13.